Speed construction of low-energy house with panel system Topkimall

Our company KIMALL will fulfill terms, which are promised. It is not just false advertising promise. In this section we will explain how time and technologies influence the construction progress of prefabricated familial houses KIMALL .

Progress of construction - the average construction time from finished foundation slab till the house is finished, is only 8 weeks.

1. House as  a unit, is always built on a finished and dry concrete foundation slab. There are cases where the construction period of the foundational slab will exceed the construction of the whole  house. Of course, this only happens if complicated landscape adjustments and preparatory construction work occurs.

2. Complete construction of prefabricated blocks and anchors with walls  - 7 days

3. The building is completely covered with roof - 14 days

4. External tile materials - 21 days

5. Internal preparatory works, water, electricity, heating distribution  - 28 days

6. Paint, and ceiling insulation - 35 days

7. Internal surfaces of walls, painting - 42 days

8. Interior work, tiling, paving and flooring - to 49 days

9. Finishing the interior and exterior - in 56 days

After eight weeks, if all tiles, floor tiles, flooring and wallpaper are in stock or ordered in advance, we hand you over a finished house.